More significant progress was made today on the linac tunnel with the first concrete placement for the tunnel lid. Ninety-five trucks delivered the 950 cubic yards of concrete. Crews started at 6 a.m. and wrapped up the placement at 3 p.m. Looking ahead, workers will start installing more structural steel for the tunnel lid on Monday. The section of lid they will focus on will take about two weeks to install.

Michigan State University (MSU) operates the Facility for Rare Isotope Beams (FRIB) as a user facility for the U.S. Department of Energy Office of Science(link is external) (DOE SC), with financial support from and furthering the mission of the DOE‑SC Office of Nuclear Physics. FRIB is registered to ISO 9001, ISO 14001, ISO 27001, and ISO 45001.