• 8 December 2017

Share this article:

Share this article:

The DOE-SC Office of Project Assessment’s (OPA) review of FRIB was held 5-7 December. The main focus of the review was to assess overall FRIB Project progress since the last review in June 2017, with a focus on technical progress.

The review committee was organized into four subcommittees, and FRIB staff gave 51 presentations.

The OPA assessed all aspects of the FRIB Project – technical, cost, schedule, management, and environmental safety and health – and found that FRIB is making appropriate progress toward completion and is well-managed. The review committee answered all charge questions affirmatively.

DOE has tentatively scheduled the next FRIB Project progress review for 22-24 May 2018.

Michigan State University (MSU) operates the Facility for Rare Isotope Beams (FRIB) as a user facility for the U.S. Department of Energy Office of Science(link is external) (DOE SC), with financial support from and furthering the mission of the DOE‑SC Office of Nuclear Physics. FRIB is registered to ISO 9001, ISO 14001, ISO 27001, and ISO 45001.

Michigan State University U.S. Department of Energy